Dette er udgangspunktet, men Huscompagniet forbeholder sig retten til at tilpasse programmet.
Opstart | 19/10/2017 |
Sokkel Montage | |
Sokkel Færdig | 03/11/2017 |
Bagmur Montage | 07/11/2017 |
Spær | 20/11/2017 |
1.lev Montage | 20/11/2017 |
Ventilation montage | 22/11/2017 |
El 1 Grov | 23/11/2017 |
Vinduer | 07/12/2017 |
VVS 2. Grov | 08/12/2017 |
Tagsten Montage | 11/12/2017 |
Lofter Montage | 11/12/2017 |
Inv. Murer montage | 14/12/2017 |
Affugter | 15/12/2017 |
Maler | 08/01/2018 |
Klinker Montage | 02/01/2018 |
Formur Montage | |
HTH Montage | 22/01/2018 |
3.lev Montage | 25/01/2018 |
El 2 Montage | 26/01/2018 |
VVS 3. Montage | 30/01/2018 |
Indreg. Nilan | 30/01/2018 |
Granulat | 02/02/2018 |
Worsøgulv | 31/01/2018 |
Rengøring | 05/02/2018 |
Maler Finish | 06/02/2018 |
Fuge | 09/02/2018 |
Trykprøve | 19/02/2018 |
Foraflevering | 13/02/2018 |
Aflevering | 28/02/2018 |